Pulled Back in Through the Engineer You Hired
On a 20,000 square foot office renovation, the architect hired the mechanical engineer as its own sub-consultant. The owner paid about $107,000 in HVAC change orders and sent the demand to the architect, who had hired the engineer. Months of silence angered the owner. A year later the owner sued only the engineer, and the architect was pulled back in through a third-party claim. What helped: a specification requiring shop drawings, and the dispute clause.
If you hire the engineer, the owner sees their mistake as yours. Answer early, even to deny.